From March 14 to 16, Amangeldy Sattarov was on a working visit to Aktobe region, where he held a meeting with the head of the region Askhat Shakharov. At the meeting the parties discussed the construction of external engineering networks of comfortable schools. To date, the Akimat of the region is ready 5 PSD of external IKI, which received a positive conclusion of non-departmental expertise. Another 9 will be finalized by the end of this month.
At the same time the work on development of design and estimate documentation for improvement of adjacent territories is being carried out. Recall that local executive bodies also provide access roads, parking lots, sidewalks, street lighting and bus stops for future educational institutions.
During his working trip Amangeldy Sattarov visited construction sites of 14 comfortable schools, which are being built in Aktobe region. At the sites they discussed details on the share of local content. To support TNA, namely the producers of facing materials in the region, it was decided to increase the width of the foundation of the comfort schools. This change will allow to apply bricks, which are produced in Aktobe region.

The pace of work of "BIGlobal" and "Bazis Construction" LLP is not satisfactory, in connection with which it was instructed to organize the construction process in 2-3 shifts. This was discussed at the meeting of Amangeldy Sattarov with Deputy Akim of the region Asylbek Esenbayev, which was held on March 15. At the meeting, the parties also checked the clock on comfortable schools, the delivery date of which is scheduled for September 1, 2024.
In total, within the framework of the national project "Comfortable School" in the region it is planned to build 18 educational institutions of new format, 14 of which will open their doors by the end of 2024.